a

Neenah Water Treatment Facility

May 11, 2006

This project is part of a 20 million dollar expansion to the Neenah Water Treatment Facility. The term of the project was two years and consisted of a significant expansion and renovation of the existing facility. Northern Electric, Inc.'s task was to install a new 4000 amp electrical service, a 1250 KW generator and back feed the existing service without shutting the facility down. During the process it took careful coordination between Northern Electric, Inc.'s project managers the owner and the general contractor as well subcontractors to do what needed to be done and keep the facility on line the whole time.